Viaduct Harbour for Americas Cup 2000

INTRODUCTION

For the Americas Cup 2000 the viaduct harbour needed to be reconfigured and extended to allow for all the syndicate bases prior to the competition commencing. We prepared and monitored the construction programme for Fletcher Construction.

Included new reclamation areas with piled seawalls and mudcrete fill.

250,000 cubic metres of dredged sandstone deposited 150km away in an Auckland Offshore disposal area